SOUTHEAST PARK CONCESSION PROJECT
DATE
STATUS
DESIGN N/A 100%
PERMITTING 8/15/2019 100%
CONSTRUCTION 9/16/2019 90%
FINAL CLOSEOUT / GRANT REIMBURSEMENT
10/1/2019 33%
VETERANS PARK / MARINA RESTROOM PROJECT
DATE STATUS
DESIGN N/A 100%
PERMITTING 9/2019 100%
CONSTRUCTION 9/2019 75%
FINAL CLOSEOUT / GRANT REMIBURSEMENT 10/31/2019 0%
FIREFIGHTERS PARK PROJECT
($200,000 GRANT)
DATE STATUS
DESIGN 3/1/2019 100%
PERMITTING 5/29/2019 100%
CONSTRUCTION 6/24/2019 95%
FINAL CLOSEOUT / GRANT REIMBURSEMENT
10/6/2019 25%
DOG PARK PROJECT
DATE
STATUS
DESIGN 7/10/2019 90%
PERMITTING TBD 0%
CONSTRUCTION TBD 0%
FINAL CLOSEOUT / GRANT REIMBURSEMENT
TBD 0%
BLUEWAY TRAIL PROJECT
($200,000 GRANT)
DATE STATUS
DESIGN 7/2019 30%
PERMITTING TBD 0%
CONSTRUCTION TBD 0%
FINAL CLOSEOUT / GRANT REIMBURSEMENT
TBD 0%
SOUTHGATE PARK PROJECT
($200,000 GRANT)
DATE
STATUS
DESIGN
9/1/2019 90%
PERMITTING TBD 0%
CONSTRUCTION TBD 0%
FINAL CLOSEOUT / GRANT REIMBURSEMENT
TBD 0%